Covidien Building 20

Project Cost:
$250,000

  • Replace central station, hot and chilled water piping and fin tube piping.
  • This project was completed while the building was occupied without the interruption to the client’s daily work schedule.
  • Hoisting was performed on weekends.
  • HVAC modifications took place after normal work hours.
  • Replace central station, hot and chilled water piping and fin tube piping.
  • This project was completed while the building was occupied without the interruption to the client’s daily work schedule.
  • Hoisting was performed on weekends.
  • HVAC modifications took place after normal work hours.